16 Billion Cut

The Federal Government Is No Longer Pursuing These Road Projects

With “Transport ’45,” the federal government is cutting numerous road projects. A total of 31 projects worth approximately 16 billion francs are being scrapped. These include expansion projects that were already rejected in 2023. In their place, the federal government is exploring operational measures. An overview of the consequences.
Diese Strassenprojekte verfolgt der Bund nicht weiter. The Federal Government Is No Longer Pursuing These Road Projects. La Confédération renonce à ces projets routiers.
© iStock
THE KEY POINTS IN BRIEF
• “Transport ’45” is not proceeding with 31 highway projects totaling approximately 16 billion francs.
• These include the Le Vengeron–Nyon and Schönbühl–Kirchberg expansions, which were already rejected in 2023.
• Instead, the federal government is exploring operational measures such as the temporary use of emergency lanes.

31 Road Projects Worth 16 Billion Francs

The fed­er­al gov­ern­ment is no longer pur­su­ing many projects. Thir­ty-one projects from the so called STEP pro­gram are being scrapped. Togeth­er, they cost around 16 bil­lion francs. In doing so, the fed­er­al gov­ern­ment is set­ting clear pri­or­i­ties, as funds are lim­it­ed.

Le Vengeron–Nyon and Schönbühl–Kirchberg

Two projects are of par­tic­u­lar focus. The Le Vengeron–Nyon and Schönbühl–Kirchberg expan­sion projects are being scrapped. The pub­lic reject­ed them as far back as 2023. Con­se­quent­ly, the fed­er­al gov­ern­ment is act­ing accord­ing­ly. The referendum’s impact is thus still being felt today.

Operational Measures as a Replacement

This deci­sion does not mean a stand­still. Instead of the expan­sion, the fed­er­al gov­ern­ment is explor­ing oper­a­tional mea­sures. These include, for exam­ple, the tem­po­rary use of emer­gency lanes. Such mea­sures are intend­ed to ease traf­fic con­ges­tion dur­ing peak hours. They are less expen­sive and can be imple­ment­ed more quick­ly.

What the Cancellation Triggers

The list of can­celed projects is like­ly to spark debate. Affect­ed regions will lose planned traf­fic relief. Oth­ers wel­come the can­cel­la­tion for envi­ron­men­tal rea­sons. An ETH report pro­vides the basis for the selec­tion. Read more about this in the arti­cle on pri­or­i­ti­za­tion.

The following projects are specifically slated for cancellation

  • N1 Elar­gisse­ment à six voies Le Vengeron – Cop­pet (GE/VD)
  • N1 Elar­gisse­ment à six voies Cop­pet – Nyon (GE/VD)
  • N1 Nyon – Aubonne (VD)
  • N1 Elar­gisse­ment à six voies Aubonne – Morges Ouest (VD)
  • N1 Grand Con­tourne­ment de Morges (VD)
  • N1 Elar­gisse­ment à six voies Echangeur Vil­lars-Sainte-Croix – Cos­son­ay (VD)
  • N1 Elar­gisse­ment à six voies Cos­son­ay – La Sar­raz (VD)
  • N1 La Sar­raz – Cha­vor­nay (VD)
  • N1 Cha­vor­nay – Essert-Pit­tet (VD)
  • N1 6‑Spurausbau Schön­bühl – Kirch­berg (BE)
  • N1 Kirch­berg – Luter­bach (BE/SO)
  • N1 Wig­ger­tal – Oftrin­gen (AG)
  • N1 Oftrin­gen – Aarau West (AG/SO)
  • N1 Aarau West – Aarau Ost (AG)
  • N1 8‑Spurausbau Wet­tin­gen – Dietikon (AG)
  • N1 Dietikon – Lim­mat­tal (ZH)
  • N1 Glatt­ta­lau­to­bahn inklu­sive Aus­bau Wallisellen/Flughafen (ZH)
  • N1 Brü­tisellen – Win­terthur-Töss (ZH)
  • N1 6-/8‑Spu­raus­bau Umfahrung Win­terthur (ZH)
  • N1 St. Gallen-Neu­dorf – Meggen­hus (SG)
  • N3 6‑Spurausbau Augst – Rhe­in­felden (AG)
  • N3 Zürich Süd – Thal­wil – Wädenswil (ZH)
  • N3 Wädenswil – Richter­swil (ZH)
  • N3 Schin­del­le­gi – Pfäf­fikon SZ (SZ)
  • N4 Erweiterung Cholfirst­tun­nel Schaffhausen (SH/ZH)
  • N6 Muri – Rubi­gen (BE)
  • N8 Sar­nen Nord – Alp­nach – Lop­per (OW)
  • N9 Vil­lars-Sainte-Croix – Vennes (VD)
  • N9 Vevey – Mon­treux (VD)
  • N11 Zürich Nord – Kloten Süd (ZH)
  • N14 Buchrain – Rüti­hof (LU/ZG)

On the future of mobil­i­ty

Special Feature: “Transport ’45”

This arti­cle is part of the “Trans­port ’45” spe­cial series. In this series, we pro­vide an overview of Switzerland’s major trans­porta­tion pro­gram through 2045. We exam­ine the expan­sion of rail and road net­works, com­muter trans­porta­tion, and financ­ing. Each part delves deeply into a spe­cif­ic top­ic while remain­ing easy to under­stand on its own. You can find the com­plete overview and all oth­er arti­cles on our “Trans­port ’45” overview page .
Which high­way projects are being can­celed?

31 projects from the STEP pro­gram, includ­ing Le Vengeron–Nyon and Schönbühl–Kirchberg.

The fed­er­al gov­ern­ment is eval­u­at­ing oper­a­tional mea­sures. These include the tem­po­rary use of emer­gency lanes.

this page has been automatically translated.

Comments:

Leave a Reply

Your email address will not be published. Required fields are marked *

Ähnliche Beiträge

TECTRUM RS32 Roll-off Tipper

The new powerhouse from Meiller

The new TECTRUM RS32 hook-lift from MEILLER offers a 32-tonne rated load capacity and high load-bearing capacity. Thanks to its modular design, wide range of equipment options and international variants, it is suitable for demanding applications. It will be unveiled at IAA Transportation 2026.

Vehicle Development

Audi Develops the Nuvolari in 405 Days

It took Audi just 405 days from the first sketch to a drivable prototype to develop the new Nuvolari. An autonomous project team is said to have made this pace possible. However, that number only describes part of the journey. For the industry, there’s a bigger question behind it: How fast is Europe still developing?

New Registrations in July

Leapmotor Reaches 1.2 Percent Market Share in Switzerland

Leapmotor reports a record for July 2026. Globally, the Chinese brand delivered over 100,000 vehicles in a single month for the first time. In Switzerland, it achieved a 1.2 percent market share in July. In the electric vehicle segment, the figure was 3.2 percent.