The ETH report and how the federal government is reprioritising transport projects
Two problems triggered the review. Significant cost overruns were emerging in the rail expansion. In addition, voters rejected the 2023 expansion step for the national roads in November 2024. DETEC therefore commissioned ETH Zurich on 28 January 2025 to carry out an overall assessment (Federal Council, 19 June 2026 (in German)).
Who wrote the report
The report was written by Prof. Ulrich Weidmann and Dr Michael Nold of the Institute for Transport Planning and Systems at ETH Zurich. It is dated 9 October 2025 (ETH summary (in German)).
How the report assesses projects
The authors examined around 500 projects in 226 items with a volume of CHF 112.7 billion. Of this, CHF 62.2 billion related to rail, CHF 39.1 billion to roads and CHF 11.4 billion to agglomerations. The authors assessed all modes of transport using simple, predominantly qualitative criteria. They then divided the projects into six priority levels. In addition, technical analyses by ARE, FEDRO and FOT fed into the DETEC proposal.
Consequences for project selection
The reprioritisation has visible consequences. In rail, 68 small to medium-sized projects that had already been approved are being dropped, worth around CHF 2.5 billion. In roads, 31 projects worth around CHF 16 billion are affected. The federal government is thus concentrating funds on the most important bottlenecks.
Criticism and debate
The method was controversial in the consultation. Affected regions such as Eastern Switzerland question the selection, while others welcome the clear prioritisation. The consultation closed on 9 October 2026. Parliament will have the final say when it debates the dispatch from 2027.
Special Feature: “Transport ’45”
This article is part of the “Transport ’45” special series. In this series, we provide an overview of Switzerland’s major transportation program through 2045. We examine the expansion of rail and road networks, commuter transportation, and financing. Each part delves deeply into a specific topic while remaining easy to understand on its own. You can find the complete overview and all other articles on our “Transport ’45” overview page.
Why did DETEC commission a report?
Because of cost overruns in the rail expansion and the rejection of the 2023 expansion step for the national roads in November 2024.
Who wrote the report?
Prof. Ulrich Weidmann and Dr Michael Nold of ETH Zurich.
How many projects were assessed?
Around 500 projects in 226 items with a volume of CHF 112.7 billion.